EWRB Home
Electrical Workers Registration Board



Profile

Contacts

Services

What's new

What's new

Email

Links

Training Providers

Licences

Overseas Qualifications

Complaints

Online Services

Publications

Previous PageTable Of ContentsNext Page

3. Accidents

The Energy Safety Service recently published its summary of reported accidents.

As part of its strategic goal to make all information available the Board will reproduce the summary of reported accidents that relate to registered workers and trainees in this and future issues of ELECTRON.

The Board wishes to advise that any conclusions relating to the accidents reported are conclusions of the Energy Safety Service.

Accident 1

A trainee electrician working in a substation received burns to his hands and chest when he came in close proximity to live 11,000 bushings on a bank of capacitors.

The trainee's task was to isolate the capacitor bank and then examine the metalwork for rust and carry out repairs.

The 33,000 volt section of the substation had been isolated and the plastic covers of the capacitors removed.

When the trainee approached the capacitor bank to inspect it, a flashover occurred.

The trainee received burns and was found lying on the ground.

It was later discovered that isolating the 33,000 volt section of the substation did not isolate an 11,000 volt capacitor bank.

The company concerned reviewed its procedure for working in substations.

Accident 2

A trainee electrician was fitting a miniature circuit breaker for a new circuit in a switchboard installed at a college.

The trainee had isolated the switchboard, but when a teacher complained that the computers were not working, the trainee restored the power and continued working.

The trainee was having problems with the switchboard connection not lining up with a MCB termination and as he attempted to adjust the connection, his pliers contacted a busbar, causing a flashover.

The trainee received burns to his finger as a result.

Most of the MCB rail connection block was melted, showering blobs of copper inside the switchboard.

The company concerned reviewed procedures for working 'live' to ensure every effort was made to isolate power.

Accident 3

An 11,000 volt switchboard at a major substation was being replaced over a three-month period.

The switchboard had been livened, the access permit for the stage of the project having been signed off and returned.

A trainee electrician was assigned the task of removing temporary cables from one new circuit breaker cabinet for transfer to another.

The trainee was working with an electrical fitter who was to wire control and metering circuits on the switchgear.

A second cabinet was not available for re-termination of the cables until its metering had been calibrated and tested by another team still awaiting an access permit.

Once the tasks were assigned, the supervisor proceeded to mark panels not being worked on that day with crosses in red tape.

The trainee and the electrical fitter removed the back cover from the second cabinet, apparently in order to change over the cable gland plate.

The trainee and electrical fitter may not have realised the cable termination was live, having been confused by the absence of a red cross on the panel. No access permit was held for this task.

The metering calibration team was preparing for work in front of the cabinet when there was an explosion in the back, and the fitter and trainee ran outside with their clothing on fire. Fellow workers extinguished the flames and poured on water until emergency services arrived. Both the trainee and the fitter had received extensive burns, from which the trainee died soon after.

Evidently one of the men came too close or contacted the live 11,000 volt terminals, initiating a flashover. The major causes of the accident were the failure to follow the industry safety rules regarding access permits, the use of an informal system of marking the permit area and poor hazard identification procedures.

Accident 4

A meter test technician was performing calibration tests on a revenue meter when he received an electric shock from a test lead on a bench test unit. He was taken to hospital for ECG tests.

The technician had forgotten to isolate the test bench when making the connections. He was advised to obtain registration as an electrical service technician. Improvements to the safety of the test room were also recommended.

Accident 5

A line mechanic received flash burns to his eyes when he applied portable earths to a live 33,000 volt overhead line in a substation structure.

The 33,000 volt SF6 circuit breaker was opened and the breaker panel indicated that the mechanism had opened but, when the line mechanic tested the lines for isolation, he found one was still live. He discussed the test result with a switchroom operator, who suggested that it was possibly induction and he should carry on and earth the lines. As the line mechanic applied the earths, there was an explosion and the lines tripped. One of the contacts on the circuit breaker was not fully open.

The company subsequently reviewed its procedures on testing and the use of voltage detector probes, requiring further tests to be performed when in doubt.

 

Previous PageTable Of ContentsNext Page

Return to TopReturn to Top

|EWRB Home|Profile|Contacts|Services|Publications|What's New|Email|Links|Training|
|Forms|Overseas|Complaints|Online Services|DBH Home|Privacy Statement|govt.nz|

Page Last Modified: 2006-08-31

This site uses cookies to track and analyse usage.

Department of Building and Housing home page.